Construction contract Party A: Party B: According to the "Contract Law of the People's Republic of China", "Construction Law" and the relevant state laws and regulations, the following works will be contracted to Party B construction. Combined with the specific circumstances of the project, in order to clarify the responsibility to ensure the quality of the project and the duration of the project, the two sides fully agreed to sign this contract, in order to comply with.

First, stainless steel door set project content: building elevator stainless steel door set materials and installation

Second, stainless steel door set project cost: unit project unit price, the amount of work actually occurring according to the measurement of the amount of work calculated, the total cost of stainless steel door set of this project is calculated by multiplying the unit price of each unit of work by the amount of their respective summary of the project. Unit price is as follows: 1, stainless steel door set hanging marble: 2, stainless steel door set: yuan / square meter; grinding edge: yuan / m; bottom door edge: yuan / m (including fabric and grinding edge).

III. Contracting method: contracting work and materials.

Duration: within days from the date of signing the contract. Start time: month, completion time: year month. During the construction period, such as the occurrence of force majeure natural disasters, the duration of separate negotiations.

V. Payment and Settlement of Project Price: After the completion of the stainless steel door cover project, pay up to 70% of the total project cost, within 5 days after the acceptance of the project, the project payment will be allocated to 90% of the total project cost; the rest of the 10% will be paid as a warranty, and will be settled within 7 days upon the expiration of the warranty period. (Note: Party B must provide official invoices that meet the financial requirements). 1/3 page

Sixth, stainless steel door set quality and acceptance standards: quality in line with GB50300-2001 and the relevant norms of the acceptance criteria, and the requirements of the appearance of neat, beautiful, clean cut in line with the design requirements. All materials must comply with national standards and drawings, materials to the scene after the arrival of the technical information must be the same with the goods. If the use of unqualified materials or non-agreed brand, and construction quality does not meet the qualified requirements, Party A has the right to unilaterally abrogate the contract, so that Party B to withdraw from the scene, and all the losses caused by Party B bear. (A), stainless steel door cover materials: a complete set of no color difference, inclusions, scars, smooth and delicate surface, rounded and neat modeling, recognized by the construction side. (B), stainless steel door set dry hanging construction: smooth surface, uniform seams, no color difference, smooth and delicate, round and neat.

VII. Site: The construction site is the status quo, the construction of the project in the event of other circumstances, by Party B to resolve their own.

VIII. Warranty period of the project: twelve months from the date of completion and acceptance.

Nine, the responsibility for breach of contract: Party A responsibility: 1. responsible for coordinating the relationship between civil engineering and Party B construction team; 2. supervise the construction of Party B in accordance with the operating procedures, the quality of the acceptance of the standard does not meet, the right to order correction; the use of all the materials in the project, in accordance with the quality of the requirements to be supervised and recognized. Party B's responsibility: 1. According to Party B's design drawings, combined with the actual preparation of the construction program, and submit to Party A and the supervision unit for review and approval; obey Party A, supervision of the management, strictly according to the construction procedures and construction program construction to ensure that the project meets the GB50300-2001 quality acceptance of the qualified standards. 2/3 page 2. All materials used in the project should reach the qualified standard, and with the Construction Bureau for the record procedures, should be tested and inspected materials should be reported in a timely manner; to provide the construction unit with complete construction technical information. 3 seriously organize safe production, on-site construction personnel should apply for insurance, engineering construction accidents, Party B is fully responsible for. 4. 4. Party B shall promptly rework and bear all the costs if the quality of the project fails to meet the requirements. 5. delay in the construction period, every day over the fine of two thousand yuan, on-site installation of electricity meters and pay the electricity bill. Matters not yet resolved, consultation or sign a separate supplementary agreement X. The contract is a four copies, A and B each two copies. Party A representative: Party B representative: Party A: Party B.

en_USEN